CALIFORNIA Home Improvement Contract Law Test Question 2

 

2. My California Home Improvement contract tells the approximate date when work will start and when work will end.

CORRECT ANSWER IS YES

 

 

Here is why: This is covered under section 7159 of the California Business and Professions Code which states:

10) The contract shall address the commencement of work to be performed in substantially the following form:

(A) A statement that describes what constitutes substantial commencement of work under the contract.

(B) The Heading: "Approximate Start Date."

(C) The approximate date on which the work will be commenced.

11) The estimated completion date of the work shall be referenced in the contract in substantially the following form:

(A) The heading "Approximate Completion Date."

(B) The approximate date of completion.